Description
We've placed the first beam on the North Island Main Trunk (NIMT) overbridge, the northernmost structure on Ōtaki to north of Levin: Te Pae o Tararua.
This single span bridge has 7 beams, each 26-metres-long and weighing 55 tonnes. Rising 5.5-metres above the rail line, it'll carry 2 lanes of traffic on the new expressway, with a shared user path on one side.
After all the beams are in place the concrete bridge deck will be poured, followed by earthworks on either side, enabling the bridge to be used by construction vehicles later this year.
This'll be the first bridge completed in the project's northern section, allowing roadworkers more efficient access to the northern end of the site, where a roundabout will connect the new expressway to the existing State Highway 1.